Q – When will the freeway be completed?

A – The southern part of the freeway, between US 50 East and US 50 West / S. Carson Street will be built in two separate Phases. The portion between US 50 East and Fairview Drive will be constructed first. Scheduled completion is mid-2009. The portion between Fairview Drive and US 50 West / S. Carson Street will then be constructed, scheduled completion is 2012 - 2014 subject to funding availability.

Q – Can you provide a summary of the major items and quantities for the Phase 2A construction contract?

A – See table below.

CARSON CITY FREEWAY PHASE 2A
SUMMARY OF MAJOR ITEMS & QUANTITIES*

ITEM APPROXIMATE QUANTITY
ROADWAY EXCAVATION 119,500 Cubic Yards
DRAINAGE /STRUCTURE RELATED EXCAVATION 74,000 Cubic Yards
BORROW EMBANKMENT 477,000 Cubic Yards
BORROW EMBANKMENT (SPECIAL) (55R Value Minimum) 17,600 Cubic Yards
TOPSOIL 13,000 Cubic Yards
HYDRO-SEEDING 80 Acres
TYPE 1 CLASS B AGGREGATE BASE 219,000 Tons
PLANTMIX SURFACING (TYPE 2C) (WET) 53,200 Tons
PLANTMIX OPEN-GRADED SURFACING (3/8-INCH) (WET) 6,300 Tons
CONCRETE BARRIER RAIL (TYPE FA) 18,700 Linear Feet
CLASS AA CONCRETE, MODIFIED (MAJOR) 8,000 Cubic Yards
(Mainly for Reinforced Concrete Box & Bridges) 5,500 Cubic Yards
CLASS EA CONCRETE, MODIFIED (MAJOR) 483,000 Pounds
REINFORCING STEEL 14,000 Pounds
REINFORCING STEEL (EPOXY COATED) 3,500 Linear Feet
15-INCH REINFORCED CONCRETE PIPE, CLASS III 1,300 Linear Feet
42-INCH REINFORCED CONCRETE PIPE, CLASS III 1,700 Linear Feet
   
* Quantities shown are intended to provide information about the general magnitude of some of the major items anticipated for use on this project. NDOT makes no claim that they represent actual bid items and/or quantities.

Q – Will there be a bicycle/walking path along the freeway corridor?

A – A multi-use path was constructed as part of Phase 1B the freeway from Broadleaf Lane to US 50 East. It is separated from the freeway and will cross various streets that are near the freeway. Another multi-use path has been designed to connect the Linear Ditch Park multi-use path to the Carson City bicycle path system at Butti Way and E. Fifth Street. This path will be constructed as part of the Phase 2A project.

Q – Why was the northern part of the freeway built first when the biggest benefit to traffic will be on the south end of Carson City?

A – Work was started to the northern part of the freeway because more of the right-of-way needed had been purchased, allowing the construction to start sooner on this end of the project.

Q – Why can't the freeway location be moved to a less disruptive part of the city?

A – The location of the freeway has been planned for many years. The location is the preferred alternative that was selected in the late 1980s, in consideration of many factors using a process known as an environmental assessment. Much of the right-of-way needed for the freeway has been purchased while it is still undeveloped, when it is less costly and less impacting to others. The freeway will be designed to lessen negative impacts to adjacent property owners. An example of the mitigation, or reduction of impacts, will be the construction of walls to block and thereby reduce the traffic noise to adjacent residential properties.

Q – Where will I be able to get on and off of the freeway?

A – The freeway is a limited access facility similar to the I-80 and US 395 freeways in Reno.  Two half-interchanges and four full interchanges are planned for the 8-mile long freeway. 

A southbound freeway off-ramp and a northbound freeway on-ramp from N. Carson Street is located near Bonanza Road.  This is one of the half-interchanges constructed in the Phase 1B project.

A southbound freeway on-ramp and northbound freeway off-ramp is located at Arrowhead Drive.  This is the second half-interchange constructed in the Phase 1B project.

Access on and off of the freeway, in both northbound and southbound directions, will be provided at the following interchange locations (full interchanges):

College Parkway
US 50 East
Fairview Drive
US 50 West & South Carson Street

Q – How do I obtain additional information about the project?

A – A wide variety of project information can be found throughout this site.  If an item you are interested in is not contained on the site, feel free to e-mail us your question by using the Comments page.

YOUR COMMENTS